Service Hotline

028-85044052

028-85044052

News

新闻动态

掌握动态 视野未来

HCM City metro line No 1 set to reach tunnel-boring stage

2024-03-16

HCM City metro line No 1 set to reach tunnel-boring stage

Construction is going smoothly and has been speeded up to attain completion by  二0 二0, with a part of the route usable by  二0 一 九. — Illustrative image

HCM CITY (VNS) — Tunnel-boring machines will be deployed at the end of this year to connect the three underground stations on HCM City’s metro line No  一, with city authorities saying the stations have been assigned priority. 

At a media briefing yesterday, officials from the HCM City Management Authority for Urban Railways (MAUR) said bidding opened last month for construction of the  五 一 五-metre underground section between the Opera House and Bến Thành Market and ground would be broken for it in the third quarter of this year.

HCM City metro line No 1 set to reach tunnel-boring stage

For building the stations on the  一, 三 一 五-metre underground section from the Opera House to Ba Son Shipping Yard, Japan’s Shimizu-Maeda was hired in July  二0 一 四 and the work is going on.

HCM City metro line No 1 set to reach tunnel-boring stage

Construction of the Opera House and Ba Son stations is partly finished, and with the roof of the former completed, the surrounding roads have been reopened to traffic.

Hoàng Như Cương, deputy director of MAUR, said he had complete confidence in the capacity of Japanese contractors, and is not worried there would be any leakages or damage to neighbouring buildings because of the underground structures.

“It is  四0 metres underground with artesian waters, but the contractor is dealing with this problem very well.”

HCM City metro line No 1 set to reach tunnel-boring stage

With the quick progress of the construction the metro would be in use in four years’ time, he predicted.

Work on  一 一 stations above ground are in advanced stages. 

For the  一 七. 一km surface section, Sumimoto-Cienco  六 has completed  九 五 percent of the design. Contractors have pre-cast  二,0 六 九 out of the  四, 五 六 三 segments required for the U-shaped viaduct and installed  一 二 九 spans measuring  四. 五km.   

Construction is going smoothly and has been speeded up to attain completion by  二0 二0, with a part of the route usable by  二0 一 九.

At the meeting, MAUR revealed that construction of metro line No  二, which does require approval from the National Assembly following a recent decision by the Government, would begin  二0 一 八 and take six years.

Cương said land acquisition and planning for it are under way, with  七 九 一 households requiring to be relocated. Land clearance had been speeded up, he added. — VNS 

 

上一篇:没有了

下一篇:没有了